QUARTERLY ACTIVITIES REPORT - DEC 2025
| Stock | Aeris Resources Ltd (AIS.ASX) |
|---|---|
| Release Time | 29 Jan 2026, 9:59 a.m. |
| Price Sensitive | Yes |
Aeris Resources Reports Quarterly Activities for Dec 2025
- Group copper equivalent production of 10.1kt at AISC of A$4.21/lb Cu eq
- Gold production at Cracow 11.1koz, ahead of plan and costs in line
- Successful $80M placement and $21.6M oversubscribed SPP, repaid $50M WHSP Facility
Aeris Resources Limited reported its quarterly activities for the period ended 31 December 2025. The company achieved group copper equivalent production of 10.1kt at an AISC of A$4.21/lb Cu eq. Gold production at Cracow was 11.1koz, ahead of plan, with costs in line. Copper production and costs at Tritton operations were also in line with plan. The company significantly improved its cash and receivables position to $106.4M, following the successful completion of an $80M placement and $21.6M oversubscribed share purchase plan. Aeris also fully repaid and cancelled the $50M ($40M drawn) WHSP Facility, materially deleveraging the balance sheet. Exploration results were encouraging, with high-grade intersections returned from drill testing resource extensions at Avoca Tank and Budgerygar (Tritton). Drilling also commenced at Golden Plateau (Cracow). The company received development consent for the Constellation project, a critical step towards construction.
For FY26, Aeris provided the following guidance: Copper production of 24-29kt, Gold production of 44-56koz, Silver production of 240-293koz, and Copper equivalent production of 40-49kt.
Aeris continues to focus on organic growth projects, an aggressive exploration program, and investigating strategic merger and acquisition opportunities. The company remains committed to building strong partnerships with key stakeholders.