SA1 Construction Update
| Stock | Delorean Corporation Ltd (DEL.ASX) |
|---|---|
| Release Time | 25 May 2026, 8:32 a.m. |
| Price Sensitive | Yes |
Delorean Corporation SA1 Bioenergy Facility Construction Update
- Construction of SA1 Bioenergy Facility is 75% complete.
- Project on track for acceptance of waste in August 2026.
- First renewable gas injection planned for November 2026.
- Strong safety performance with zero lost time injuries.
- SA1 serves as a template for future infrastructure projects.
Delorean Corporation Ltd has announced that construction of its first 100%-owned SA1 Salisbury Bioenergy Facility in Adelaide is 75% complete. The project is on track for acceptance of waste in August 2026 and first renewable gas (biomethane) injection into the Adelaide gas network in November 2026. The facility will process 70,000 tonnes per annum of organic waste from the Adelaide metro area, producing 210 TJ per annum of renewable gas and 6,000 tonnes per annum of biogenic food grade liquid CO2. The project is maintaining a strong safety performance with zero lost time injuries recorded to date. SA1 is a template for the rollout of Delorean's shovel-ready and near-term infrastructure project portfolio, with NSW1 and VIC1 facilities expected to enter construction in CY2026.
SA1 Facility on track for August waste acceptance and November gas injection
SA1 serves as a template for future infrastructure projects, with NSW1 and VIC1 facilities expected to enter construction in CY2026.