Devon Gold Mine Campaign 3 Processing Commences

Open PDF
Stock Matsa Resources Ltd (MAT.ASX)
Release Time 29 May 2026, 9:34 a.m.
Price Sensitive Yes
 Matsa Resources Begins Devon Gold Mine Campaign 3 Processing
Key Points
  • Campaign 3 processing at Devon Gold Mine has started on schedule
  • Gold ore stockpiled at FMR's Greenfield plant with a 13-day window
  • Campaign 3 is 6 days shorter than Campaign 2
  • Mining on track to meet or exceed Campaign 2 ore grade
Full Summary

Matsa Resources Limited announced that Campaign 3 for processing gold ore from the Devon Pit Gold Mine has commenced on schedule. Gold ore has been stockpiled at FMR's Greenfield processing plant, allowing for a 13-day processing window. Campaign 3 is 6 days shorter than Campaign 2 due to operational requirements at FMR. Mining operations have been on track to equal or exceed the ore grade achieved in Campaign 2. The next processing campaign, Campaign 4, is planned for late July 2026, with exact timing to be advised later.