Lorelle-3H Completion & Testing Progress

Open PDF
Stock Elixir Energy Ltd (EXR.ASX)
Release Time 15 Jun 2026, 8:23 a.m.
Price Sensitive Yes
 Lorelle-3H Completion & Testing Progress
Key Points
  • Lorelle-3H Diagnostic Fracture Injection Test (DFIT) completed successfully
  • Preliminary reservoir pressure of ~6,350 psi and gas gradient of ~0.6 psi/ft
  • Stimulation stages increased to 12, including the toe stage
  • Mobilisation and rigging up of equipment underway for stimulation operations
  • Stimulation operations expected to commence towards the end of the week
Full Summary

Elixir Energy Limited (ASX: EXR) has provided an operational update on the Lorelle-3H appraisal well in ATP2056 within Queensland's Taroom Trough. The Diagnostic Fracture Injection Test (DFIT) at the toe end of the Lorelle-3H well was successfully completed, indicating a preliminary reservoir pressure of approximately 6,350 psi, consistent with expectations. The closure-pressure results for the Tinowon 'Dunk' Sandstone formation at 8,759 psi indicate the ability to maintain the fractures within the targeted formation. Due to the quality of the results observed during the DFIT and minor incremental costs, the number of stimulation stages has been increased to 12. Mobilisation and rigging up of the stimulation and well testing equipment are underway, with stimulation operations expected to commence on schedule towards the end of the week.

Outlook

Elixir Energy expects to commence stimulation operations on schedule towards the end of the week, following the successful completion of the DFIT and favorable closure-pressure results.