Critica Announces Strong Economics for Mt Lindsay Project
Key points
- Strong economics with pre-tax NPV of A$1.42 billion and IRR of 65%
- Tungsten as principal revenue contributor, accounting for 75% of modelled revenue
- Capital-efficient development with estimated pre-production capital of A$244.5 million
Full summary
Critica Limited (ASX: CRI) has announced the outcomes of the Scoping Study for its Mt Lindsay Tin-Tungsten Project in north-west Tasmania. The study outlines an underground development pathway for the project, with significant exposure to tin and tungsten. The base case scenario generates a pre-tax NPV of approximately A$1.42 billion, a pre-tax IRR of approximately 65%, and an after-tax payback period of approximately 1.9 years, against pre-production capital of approximately A$244.5 million. Tungsten is the principal revenue contributor, accounting for approximately 75% of modelled life-of-mine revenue. The project is located within an established Tasmanian mining region, with existing road access, proximity to established hydroelectric power infrastructure, and access to export infrastructure at Burnie.
Guidance
Pre-tax NPV of approximately A$1.42 billion, IRR of approximately 65%, after-tax payback period of approximately 1.9 years
Outlook
Critica plans to advance Mt Lindsay from the Scoping Study into a Definitive Feasibility Study, subject to successful completion of further studies, approvals, and securing required funding.